The
following activities are related to a given
project:
|
Activity |
Time |
|
1-2 |
8 |
|
1--3 |
6 |
|
1-4 |
4 |
|
1-8 |
4 |
|
3-5 |
7 |
|
3-6 |
2 |
|
4-6 |
6 |
|
5-7 |
5 |
|
6-7 |
9 |
|
7-8 |
5 |
A
certain type of crane is needed in carrying out activity
2-8, 3-6, 4-6, 5-7. only one crane of this type is
available.
Do
you think the project completion would be delayed due to
this? if yes, by how much. |